Closing the works on Line T2: PNRR deadlines respected
The main construction works for Line T2, the new tramway connecting Bergamo to Villa d'Almè along the 9.8 km of the new route of the former Valle Brembana railway, will be completed by June 30, 2026, in compliance with the deadline set by the PNRR.
The now imminent milestone confirms full compliance with the schedule, which saw construction start in April 2024, with alternating phases of work concerning the construction of the route, stops, parking lots, bike path, and the new depot.
Almost two years and three months after the start of the construction sites, the work is now nearing completion, confirming full compliance with the scheduled deadlines.
Over these two years, the construction of the work was carried out together with TEB by the company Milesi geom. Sergio for the infrastructure works, the partner G.C.F. – Generale Costruzioni Ferroviarie for the track and installations, and Škoda for the tram supply, all brought together in the temporary consortium of companies (RTI) in charge of the works. The Works Management and Safety Coordination were entrusted to MM S.p.A. A constant commitment that made it possible to meet the deadline set by the PNRR.
The next phases: complementary works, testing, and pre-operation
From June 30, a phase of an additional 60 days will begin, as provided by ministerial provisions, dedicated to completion works: finishing, some parking spaces, installation of cameras, information panels, and signage along the entire section.
At the same time, the phase of technical testing of the facilities and pre-operation will begin, preparatory to the issuance of the necessary authorizations for opening to public service, subject to a technical-administrative process involving the Ministry of Infrastructure and Transport and ANSFISA – National Agency for the Safety of Railways and Road and Motorway Infrastructures, which will establish the timing and methods.
TEB hopes, pending the results of the authorization process, to be able to start commercial operation of the new tram line by autumn 2026.
The status of the works along the line
The construction of the new tram infrastructure is entering its final phase, with the completion of the main infrastructure, railway tracking, and plant engineering works.
Along the 9.8 km of the new line from BG Bronzetti to Villa d'Almè, the tracks of the entire route have been laid, completing the main works related to the tramway track, which include the installation of ballast, sleepers, and tracks. Works have also been completed on road and pedestrian level crossings and line systems, including power supply systems, road and pedestrian traffic light systems, and signaling systems.
The new depot for the line, located near the Petosino stop and intended for the storage and management of new trams, as well as the civil works of the stops, has also been completed, with paving and platforms completed. The perimeter fence of the entire line has also been completed.
Interventions have also been completed in the two tunnels along the route: the artificial Maresana tunnel, where Line T2 runs underground compared to the existing roads, and the Ramera natural tunnel in Ponteranica, the only section of the line built on a single track.
Instead, in the subsequent completion phase scheduled after June 30, the realization of some complementary works and final arrangements continues.
The interchange parking lots at the BG S. Antonio and Paladina-Almè stops are completed, while the parking lot at the Villa d'Almè terminus is in an advanced stage. The works related to the Volta and Mazzi parking lots will require further completion work.
The new cycle path is also in an advanced stage: the main section has been paved and some ancillary works remain to be completed, including some external fences separating from private properties. The roundabout on the Villa d'Almè–Dalmine axis (SS470 dir) is also nearing completion, with completion expected within 60 days after June 30, as part of the final phase of complementary works.
The new trams
The fleet for Line T2 consists of 10 new Škoda electric vehicles, 33.5 meters long and with a maximum capacity of 281 passengers (66 seats, of which 64 are fixed and 2 foldable in the spaces reserved for wheelchairs). To date, 9 of the 10 trains have been delivered to Bergamo. The tenth tram, the first to be completed by the Pilsen plant in the Czech Republic in February this year, is currently at the Škoda Group plants for further testing and will be delivered to Bergamo in October.
The new vehicles will be added to the 14 already in service on Line T1, forming a total fleet of 24 trams capable of traveling on both lines.
The trams already delivered are undergoing their first running tests along the T1 Line route during nighttime hours. In a second phase, the trains will be engaged in pre-service operations along the T2 Line route.
The T2 Line
The new tram line from Bergamo to Villa d'Almè runs on the former Brembana Valley Railway, crosses 5 municipalities (Bergamo, Ponteranica, Sorisole, Almè, Villa d'Almè) and serves a population of over 240,000 inhabitants. The route runs for 11.5 km and includes 16 stops. The line is accompanied by a new 10 km cycle path, built by TEB along the San Fermo-Villa d'Almè section, connected to existing cycling networks.
In the first urban section, the Valle Brembana tramway shares the route and two stops with the Valle Seriana tramway: Bergamo FS, Borgo Palazzo. From the next new BG Bronzetti stop, which serves as an interchange between the two tram lines, the T2 continues along the route of the old Valle Brembana railway, which was discontinued in 1966. With the opening of the BG Bronzetti stop, the BG San Fermo stop was discontinued in both directions.
The route runs in reserved and protected areas, with 29 level crossings between road and pedestrian paths. The entire route is double track, except for the short 187-meter section of the Ramera tunnel in Ponteranica.
Along Line T2, a new depot was built, located near the Petosino stop, intended for the storage and management of 10 trams. The Ranica Operational Control Center, formerly the headquarters, depot, and workshop of Line T1, remains the operational core of both tram services.
The new service will be integrated with public transport in the urban area of Bergamo and with the suburban networks of Valle Brembana and Valle Imagna. Along the route, 7 park-and-ride lots will be built, for a total of 516 parking spaces, including bikes and motorcycles.